Implementation of measures

Sauerbrunn-Pöls - River widening

The floodplain management in Sauerbrunn-Pöls is included in a number of measures, by which a rich structured flow course is to be achieved to an extent of 3,0 km (together with the already realized measure St. Peterer-Au and Thalheim - St. Peter/ Judenburg). The area of Sauerbrunn itself covers an area of approx. 2.4 ha.
The following measures are going to be set:
o Construction of a 250 m long distributary
o 390 m opening of the bank protection
o Building of amphibian basins in dimension of 2,000 m²
o Initiationof of floodplain forest development of approx. 1.0 ha
o Improvement of a tributary-mouth
o Lowering of the ground in a dimension of 4,635 m² 
o Enlargment of the Naura-2000-Area of approx. 2.0 ha
The implementation of this measure was start in autumn/winter 2014 and finished in winter/spring 2015.

Actual pictures of the development you find here.

Life plus Natur Projekt

"Inneralpines Flussraummanagement

Obere Mur"

Gemeinsame Wege von Wasserbau und Naturschutz.

GerambRose 2010

Auszeichnung der Flussaufweitung Weyern mit der GerambRose 2010