Implementation of measures

Measure widening - Feistritz St. Lorenzen

The management of the wetlands belongs to a measure complex. By this complex, the course of the river in a length of 6.6 km, which is rich in structure has to be obtained (together with the already implemented measures Mauth and the structuring Preg). The measure wetlands Feistritz - St. Lorenzen has a size of about 4.3 ha.

The following measures are to be taken:


o  Opening of the bank revetment in a length of about 850 m
o  Preparation of a 760 m long branch
o  Building of ponds in the size of about 2,000m²
o  Initiation of the development of wetlands in a size of about 1.0 ha
o  Protection of the stand of the wetlands of about 1.4ha
o  Lowering of the area in the size of about 3,000m²
 

 

The implementation of the measures was finished in summer/autumn 2014.

 

Actual pictures of the building phase you find here.

 

Lageplan-gesamt
Life plus Nature Project
fjrigjwwe9r0teaser_Version:trV_text
"Inner-Alpine River Basin Management for the Upper Mur"
Realisation of measures
fjrigjwwe9r0teaser_Version:trV_text

Completion of measure Preg and Mauthof in 2012.

The measure Lässer Au was finished in december 2013, the measure Feistritz in the summer of 2014.

The implementation of the measures Apfelberg, und St. Peter started in summer/autumn 2014.

GerambRose 2010
fjrigjwwe9r0teaser_Version:trV_text
River widening Weyern awarded with the GerambRose 2010